Tuxpan Thermoelectric Power Plant

We carried out construction work at the Tuxpan power central. In the first phase, we built the numbers 3 and 4 units of the Adolfo López Mateos plant, with a capacity of 350 MW each. We carried all of the civil work, the electrical-mechanical work, and lighting and instrumentation systems. This facility has earned ISO 9000 and 9001 standard certification.

In a second phase, we built the numbers 5 and 6 units, also with a capacity of 350 MW each. We installed a fuel oil circulation system, a monobouy for unloading fuel, gas burners and a 400 Kv substation cooled with seawater.

Client:

Federal Electricity Commission

Location:

Tuxpan, Veracruz

Construction start date:

1993

Completion date:

1996